Project Management Professional (PMP) Exam Practice – Question1925

The project is nearing completion. The team is involved in a lot of different activities to close the project. They are in the process of grouping together various documents associated with financial records, contracts, internal project documentation, and client-related
documentation. What are they in the process of creating?


A.
Project Closure
B. Contract File
C. Lessons learned
D. Archives

Correct Answer: D