Project Management Professional (PMP) Exam Practice – Question1926

You are managing a contact management software project and senior management has come to you with a fast breaking project that could make the company have a significant market share boost. According to your current project schedule, your current project
is on pace to be completed in six weeks. What is the best response you can tell senior management?


A.
Managing both projects as requested by senior management
B. Telling senior management that you will consider the project once it has a charter
C. Assigning the Functional Manager on the project to finish the current project
D. Implementing crashing and fast tracking to complete your current project ahead of schedule so you can start immediately on this project

Correct Answer: B