Project Management Professional (PMP) Exam Practice – Question1927

The project charter has just been signed off. There were items in the charter that described market conditions which could affect the project and also resource limitations on the project.
These are examples of what?


A.
Assumptions
B. Constraints
C. Economic consumption
D. Authority level of the Project Manager

Correct Answer: B