Project Management Professional (PMP) Exam Practice – Question1930

What is the best reason to create a work breakdown structure?


A.
It provides authority for the Project Manager
B. It allows the project budget to be determined
C. It helps attain buy-in from the team doing the work
D. It allows the project completion date to be determined

Correct Answer: C