Project Management Professional (PMP) Exam Practice – Question1931

You are the Project Manager on the development of a 4-way fully redundant computer system for the government. The government has been very concerned about the correctness and acceptance of the work results. You are not sure what the government is
saying so you review your PMBOK Guide. What areas below will likely be involved in attaining what the government is concerned about?


A.
Scope Control and Scope Verification
B. Administrative Closure and Quality Assurance
C. Quality Planning and Quality Control
D. Scope Verification and Quality Control

Correct Answer: D