Project Management Professional (PMP) Exam Practice – Question1932

A Project Manager has completed the Scope Definition process. The customer and sponsor have shortened the schedule by four weeks and decided that the work breakdown structure will be excluded. The Project Manager informs the customer and sponsor that
this process creates the work breakdown structure for their project. Which answer best explains why the WBS is so important to a project?


A.
It provides a hierarchical diagram of the project
B. It is the foundation of the project
C. It provides templates that can be reused on other projects
D. It helps in team commitment to the project

Correct Answer: B