A new manufacturing facility is being built for a consumer electronic company. The project to create it is nearing completion and will soon begin to enter the Closing phase. This will involve a number of people, but who will ultimately approve the work of the
project?
A. Project Manager
B. The customer
C. Senior management
D. Stakeholders