The sponsor on the airport runway project has just told the Project Manager about a change he wants. He says that the change will cost 20% less and should not cause any problems to the existing environment. Which of the following should concern the Project
Manager the most?


A.
Scope impact
B. Schedule impact
C. Quality impact
D. Scope and schedule impact

Correct Answer: D