Project Management Professional (PMP) Exam Practice – Question1939

There has been a great delay in waiting to get the charter approved. It's finally complete and you are assigned as the Project Manager. Senior management wants you to begin planning as soon as possible. If you are in the process of planning the project, what is
the best way to schedule Scope Verification?


A.
At the end of every phase on the project
B. After the sponsor defines what they want the project to create
C. When the project management plan is awaiting signoff
D. When the work of the project is done

Correct Answer: A