Project Management Professional (PMP) Exam Practice – Question1940

All of the following are true about a work breakdown structure (WBS) except?


A.
The team and the Project Manager should be involved in creating it
B. It will resemble an organizational chart in appearance when complete
C. The Activity Sequencing of the WBS can be done only in parallel
D. It is a decomposition of the work of the project

Correct Answer: C