The Project Manager is working with the sponsor to attain formal acceptance on the infrastructure project deliverables. The customer is saying that seven of the deliverables are not meeting project goals, and are unusable in their present form. Upon reviewing
documentation, the sponsor explains to the Project Manager that the requirements are not accurate, to meet the needs for which the project was planned. What part of the Planning process did this problem occur?


A.
Creating the Work Breakdown Structure
B. Scope Control
C. Scope Definition
D. Scope Verification

Correct Answer: C