The Project Manager is working with the customer to gain formal acceptance on the project deliverables. The customer is saying that three of the deliverables are not meeting project goals, and are unusable in their present form. Which of the following will be
used to the problem?
A. Scope analysis
B. Team-building
C. Scope Control
D. Scope Verification
used to the problem?
A. Scope analysis
B. Team-building
C. Scope Control
D. Scope Verification