Crosswind Custom Homes is building a customer's dream house. However, rain has delayed the finish by two weeks. The schedule shows that the next activity is to install the roof, then that is followed by the shingles. This is an example of what?


A.
Mandatory dependencies
B. Lag
C. Discretionary dependencies
D. Crashing

Correct Answer: A