Project Management Professional (PMP) Exam Practice – Question1951

Crosswind Custom Homes is building a customer's dream house. However, excessive heat has delayed the finish by three weeks. The Project Manager evaluates the schedule and determines that the roofing and cabinetry could occur at the same time instead of

right after each other, as laid out in the schedule. This is an example of what?


A.
Mandatory dependencies
B. Crashing
C. Lag
D. Discretionary dependencies

Correct Answer: D