Project Management Professional (PMP) Exam Practice – Question1952

The customer has requested a five-week delay on the project while the company has winter holiday. This delay was not planned, but the union forced the issue. The company has limited resources. What is the best way to make up the five-week slip?


A.
Fast tracking
B. Integrated change control
C. Put more resources on the project
D. Crashing

Correct Answer: A