Project Management Professional (PMP) Exam Practice – Question1954

You are putting together the final schedule on your security encryption project. The problem you are having is that you don't have a consistent usage of your resources. Some are working 2 hours a day, some 16 hours a day, and there are some days when they
aren't scheduled to work at all. Which of the following below would fix this problem?


A.
Resource leveling
B. PERT analysis
C. Fast tracking
D. Crashing

Correct Answer: A