Project Management Professional (PMP) Exam Practice – Question1957

The Project Manager is creating an estimate for a housing development. This is something for which he is quite experienced. The client needs the estimate in four hours. Which of the following types of estimates make the most sense to use?


A.
Analogous
B. Gut feel
C. Bottom-up
D. Parametric

Correct Answer: A