Project Management Professional (PMP) Exam Practice – Question1960

All of the following could be considered functions of the GERT diagramming method except?


A.
Some activities may be performed only in part
B. Some activities may be fast tracked
C. Some activities may be performed more than once
D. Some activities may not be performed

Correct Answer: B