Project Management Professional (PMP) Exam Practice – Question1962

The project planning for the trade show is progressing on schedule. The Project Manager and the team are meeting to begin cost estimating. The sponsor has said that estimates must be very accurate. Which of the following estimating techniques will provide the
most accuracy?


A.
Cost estimating
B. Bottom-up estimating
C. Analogous estimating
D. Parametric estimating

Correct Answer: B