Project Management Professional (PMP) Exam Practice – Question1964

The project planning is progressing on schedule. The Project Manager and the team meet regularly and are ready to begin cost estimating. The customer needs an estimate as soon as possible. What estimating method should the team use?


A.
Cost estimating
B. Parametric estimating
C. Bottom-up estimating
D. Analogous estimating

Correct Answer: D