Project Management Professional (PMP) Exam Practice – Question1966

The IT initiative project is on schedule and under budget. The customer is pleased, but would like a scope change. As a result, a new team is brought in to help the existing team implement this scope change. Before the team arrives, senior management would
like to see where the project stands. Which of the following do you show them?


A.
Milestone chart
B. Gantt chart
C. Work breakdown structure
D. Network diagram

Correct Answer: A