Project A has a NPV of $275K US over 2.5 years. Project B has an IRR of 3.2%. Project C has a BCR of 0.89:1. Project D has four people on it and is encountering scope creep. Which of the following projects would stand the greatest chance of getting canceled?
A. Project A
B. Project B
C. Project C
D. Project D
A. Project A
B. Project B
C. Project C
D. Project D