Project Management Professional (PMP) Exam Practice – Question1969

You are the Project Manager of an engineering project for a cellular base station with a one-year schedule as defined by the project management plan. You need a spectrum analyzer. During the procurement process, you have decided to rent this equipment. The
rental cost is $506 per month.

What type of cost is this?


A.
Indirect
B. Direct
C. Fixed
D. Variable

Correct Answer: C