Project Management Professional (PMP) Exam Practice – Question1972

You are in the initial phase of a project and are doing an estimate for a project that requires a MRI lab for a hospital to be built. What is the estimate range you would use for this project?


A.
-10% to +25%
B. -25% to +75%
C. -5% to +10%
D. -25% to +85%

Correct Answer: B