Project Management Professional (PMP) Exam Practice – Question1978

Which process involves user cost estimates and the schedule to determine when these costs are expected to occur during the project?


A.
Cost Baseline
B. Cost Budgeting
C. Cost Control
D. Cost Estimating

Correct Answer: B