Project Management Professional (PMP) Exam Practice – Question1979

Activity A is worth $300, is 100% complete, and actually cost $350. Activity B is worth $100, is 95% complete, and actually cost $85 so far. Activity C is worth $200, is 75% complete, and has cost $175 so far. The total budget is $1500. What is the cost variance for
the activities listed?


A.
$0.84
B. $65.00
C. -$65.00
D. -$57.50

Correct Answer: C