Project Management Professional (PMP) Exam Practice – Question1981

A Project Manager was assigned to manage a project to develop pink widgets for the Project Managers company. The project will cost the company $650,000 over the next 12 months. It is projected that the widgets will earn the company $20,500 per month. How
much time will it take to recover the cost for this project?


A.
28 months
B. 32 months
C. 36 months

D. Not enough information

Correct Answer: B