Project Management Professional (PMP) Exam Practice – Question1982

Activity A is worth $400, is 95% complete, and actually cost $395. Activity B is worth $350, is 90% complete, and actually cost $330 so far. Activity C is worth $275, is 100% complete, and has cost $310 so far. The total budget is $2500. What is the total earned
value for the activities listed?


A.
$970.00
B. -$970.00
C. $1025
D. $1035.00

Correct Answer: A