Project Management Professional (PMP) Exam Practice – Question1985

What are seven consecutive data points on either side of the mean called?


A.
Too tight of control limits
B. A violation of the Seven Run Rule
C. Too loose of specification limits
D. Acceptable measurements

Correct Answer: B