Project Management Professional (PMP) Exam Practice – Question1987

A Project Manager is assigned to a project that is in the construction phase of a video computer
board. The Project Manager is in the process of reviewing deliverables and Work Results to gain formal acceptance. This is known as what?


A.
Quality assurance
B. Quality control
C. Scope Verification
D. Scope Control

Correct Answer: C