Project Management Professional (PMP) Exam Practice – Question1988

The company is in the testing phase of its project. It is tracking defects that come in from customers who are testing the project. Given the nature of a new project, they have a variety of defects that are being discovered. Organizing and prioritizing the defects is
becoming a challenge.
What would help them organize this better?


A.
Pareto diagram
B. Flowchart
C. Ishikawa diagram
D. Fishbone diagram

Correct Answer: A