The team is testing the work of the project and is having issues with a particular requirement showing the desired data. Which of the following can they use to isolate the problem?
A. Cost-Benefit analysis
B. Ishikawa diagram
C. Flowcharts
D. Design of Experiments
A. Cost-Benefit analysis
B. Ishikawa diagram
C. Flowcharts
D. Design of Experiments