Project Management Professional (PMP) Exam Practice – Question1989

The team is testing the work of the project and is having issues with a particular requirement showing the desired data. Which of the following can they use to isolate the problem?


A.
Cost-Benefit analysis
B. Ishikawa diagram
C. Flowcharts
D. Design of Experiments

Correct Answer: B