Project Management Professional (PMP) Exam Practice – Question1992

The Project Manager is reviewing testing output. Generally, the data looks good. He does observe seven consecutive data points on one side of the mean in a couple of areas on the control chart.

What is this called?


A.
A violation of the Seven Run Rule
B. Lucky seven gets eleven
C. Acceptable measurements
D. Too loose of specification limits

Correct Answer: A