The project is going through quality assurance. Which of the following is a key tool that will be utilized in this process?
A. Quality improvement
B. Quality audits
C. Quality testing
D. Quality management plan
A. Quality improvement
B. Quality audits
C. Quality testing
D. Quality management plan