Project Management Professional (PMP) Exam Practice – Question1998

The project is progressing. As the company starts to release the product of the project to market, the consumer isn't buying it as the company had projected. This appears to be because the company has released a lot of products before that had an excessive
number of defects. Who was ultimately responsible for these products being released with the defects?


A.
Functional management
B. Project Manager
C. The developer
D. Senior management

Correct Answer: D