Project Management Professional (PMP) Exam Practice – Question2008

The project is in a projectized environment. There are significant challenges with meeting the tight schedule of the project and personnel leaving the company. Project personnel have been complaining to senior management about the environment hoping for a
resolution. In this type of environment, who controls the resources?


A.
Project Manager
B. Functional Manager
C. Senior management
D. Project Coordinator

Correct Answer: A