Project Management Professional (PMP) Exam Practice – Question2009

You are the Project Manager working with the customer on a construction project. You are required to purchase and integrate wireless communication system throughout the construction. A contract is signed with a vendor and work has begun. Halfway through
the project, the customer decides to upgrade the equipment. This change will require changes to the signed contract. Who has the authority to change the contract?


A.
Sponsor
B. Project Manager
C. Customer
D. Contract Administrator

Correct Answer: D