Project Management Professional (PMP) Exam Practice – Question2010

The project has gone smoothly so far. The team members appear to be working with an end goal in mind and without a lot of supervision. They appear highly motivated and enjoying their work.
This is an example of what?


A.
Reward Theory
B. Theory Y environment
C. Motivation Theory
D. Theory X environment

Correct Answer: B