The project is in a balanced matrix environment. There are significant challenges with the schedule and resource constraints of the project. Project personnel have been complaining to the Project Manager about the environment. In this type of environment, who
controls the resources?


A.
Functional Manager
B. Project Manager
C. Project Coordinator
D. Senior management

Correct Answer: A