Project Management Professional (PMP) Exam Practice – Question2015

The Project Manager tells a team member on the project that she can attend some training for a new computer program. He further explains that this new skill will be used by the company in the future. He lets the team member know that he approved this training
because of the good work the team member has done on the project. This is an example of what type of power?


A.
Formal
B. Reward
C. Award
D. Compromise

Correct Answer: B