Project Management Professional (PMP) Exam Practice – Question2017

The project is progressing well but has begun to experience resource conflicts with people who are being pulled from the project by functional management for other work. What role will typically help resolve these resource issues?


A.
Senior management
B. Functional management
C. Project management
D. Sponsor

Correct Answer: A