Project Management Professional (PMP) Exam Practice – Question2018

A retail expansion project is going relatively well, but the people doing work on the project are complaining that it seems as though they answer to two bosses on the project, each with conflicting agendas. This is an example of what type of project environment?


A.
Functional
B. Matrix
C. Tight matrix
D. Projectized

Correct Answer: B