Project Management Professional (PMP) Exam Practice – Question2020

The Project Manager is in the process of planning the project. The company he works for has had issues with previous projects in which there has been confusion over who is accountable for completion of various activities and processes associated with the
projects. What document can he include in the project management plan that will help eliminate this problem?


A.
Gantt chart
B. Staffing plan
C. Organization chart
D. Responsibility assignment matrix

Correct Answer: D