The Project Manager has defined the risks for the project, performed probability and impact analysis and assigned risk owners to the risks. As the project management plan evolves where will this information end up?
A. Risk list
B. Risk trigger
C. Risk register
D. Risk response
A. Risk list
B. Risk trigger
C. Risk register
D. Risk response