Project Management Professional (PMP) Exam Practice – Question2025

On the electric company project the government implemented a regulatory change associated with the electricity sub-station upgrade project that required the company to spend an additional $400,000 US on the project. This type of cost and activity best relates to
which of the following?


A.
Known unknowns
B. Unknown unknowns
C. Management reserve
D. Risk management

Correct Answer: B