Project Management Professional (PMP) Exam Practice – Question2027

In defining a risk trigger, which of the following is most accurate?


A.
A trigger is an indicator that a risk event will occur
B. A trigger is the same as a risk
C. A trigger is an indicator that a risk event has occurred
D. A trigger is an indicator that a risk event could occur

Correct Answer: D