The Project Manager and team are planning the project. They are presently identifying things that could go differently than planned. They are also trying to identify warning signs that would show that these events could be on the verge of occurring. What is the
team doing?
A. Risk analysis
B. Risk Identification
C. Conformance to quality
D. Problem solving
team doing?
A. Risk analysis
B. Risk Identification
C. Conformance to quality
D. Problem solving