Project Management Professional (PMP) Exam Practice – Question2033

The Project Manager and team are planning a banking software project. They are discussing what could go differently than planned on the project. They are also trying to identify warning signs that would show that these events could be on the verge of occurring.
What are these warning signs called?


A.
Risk analysis
B. Triggers
C. Problem solving
D. Risks

Correct Answer: B