Project Management Professional (PMP) Exam Practice – Question2035 Ranking risks is performed in which of the following? A. Workarounds B. Risk triggers C. Qualitative Risk Analysis D. Expected monetary value (EMV). Show Answer Hide Answer Correct Answer: C Post navigation Project Management Professional (PMP) Exam Practice – Question2034Project Management Professional (PMP) Exam Practice – Question2036