Project Management Professional (PMP) Exam Practice – Question2036 Which of the following best relates to unknown unknowns? A. Schedule reserves B. Risk management C. Contingency reserves D. Management reserves Show Answer Hide Answer Correct Answer: D Post navigation Project Management Professional (PMP) Exam Practice – Question2035Project Management Professional (PMP) Exam Practice – Question2037